What are the must have period end reports, I would be advised to produce
Currently, I receive our contractors programme, and produce the following reports
1. Full Programme, with Last Period and Baseline Variances
2. Critical Path Layout
3. 4, and 8 week lookahead
4. Milestone Slippage
The programme submitted is not cost or resource loaded.
Regards
Philip
total float report and a schedule narrative