converted PowerProject programme mixed duration formats

I have converted a Powerproject file to msp, however the duration & total float formats are mixed, ie some are "15 d" and some are "3 w". I cannot see where you can change them all to days??

 

Andrew

T
Tom Boyle 👤 Member for 19 years 7 months

Andrew,

If you are running MSP 2010+ and are comfortable with vba, you can drop this into a module and run it:

Sub DurationDays()

    Dim t As Task

    For Each t In ActiveProject.Tasks

        t.Duration = Application.DurationFormat(t.Duration, pjDays)

    Next t

End Sub

 

(Method is supposedly different with earlier versions, but I have no way to test.)

Otherwise, you may be stuck with manually changing the durations, perhaps with a little clicking and dragging.

Good luck, tom

Featured Partner

Top Posters

James Williams
75 posts
Alex Lyaschenko
26 posts
xerxes
0 posts
edwin
0 posts
jhalluk69
0 posts
wilmoahyi
0 posts
Peter Holroyd
51 posts
Robert Guers
1 posts
Jerry Robinson
2 posts
Elyar Safarov
1 posts

Our Partners