Reporting!!!!

Member for

21 years 3 months

Ahu,



The thing is you have to use costs to summarize !!



Here’s the thing. If you want to summarize for example for earned value proposal than you have to (or better) use costs. What you can do is give each resource a standard cost of 1$/hr. Than costs are equal to units. Make sure that costs units linked is on on activity (resource) level







Regards



Henk


Member for

20 years 5 months

because i choose the same resourses to the activities,i supposed that the program knows it and may not summarize the valuses but show the the value of UP and UM at the high level.



THANK YOU

Member for

20 years 10 months

Misread part of the question. Unit price is also a non summable. I am not sure how you would want this summarized. I don’t think you would want the values added together.



Regards,

Bill

Member for

20 years 10 months

Resource unit of measureable is not summable. It is a text field. I guess it may make sense to show it if as in your case all of the values are identical. There is not a way to do this.



As far as UPT, again this is not a summable field for a resource assignment. You would not want to simply add the values as this is a ratio.



You would need to create a report outside of p3e/c’s report writer to do this.



Regards,

Bill