Hi all,
I am still finding my way around P6 and would like to know if anyone can giuve me a step by step outline of how to create a a 2wk look ahead filter. I am familair with creating filters but have never done one for a look ahead.My two main questions are:
- Do I use the "Earliest start date" and "Latest finish dates" instead of "Start" and "Fininsh"?
- I aslo want to include all work that is still in progress during the lookahead period regardless of when it starts or will finsh. Is this good practice to include this criteria as part of a look ahead schedule and if yes, how would I do that in combination with the dates filter in question 1 above?
Thanking ou in advance,
LP6
qyestion was 2 week not 3 or 4
To create a look a head schedule read the articles below
Three Week Look Ahead Schedule in Primavera P6
Four Week Look Ahead Schedule in Primavera P6
Hiahab all you did was copy mine
use the start and fiinsh dates do not use early and late
Display all rows ParameterIs Value HighValue
Where Start is within range of DD DD+2W
Or Finish is within range of DD DD+2W
Or Activity Status equals In Progress
Why we are using late Finish in this below Filter?????
In My Opinion below filter is enough.
this shoud do it
*
Hi all , I need to ask how to make a aevised plan using primavera or recovery plan ?
Hi all , I need to ask how to make a aevised plan using primavera or recovery plan ?
hiiii all
concerning schedule update i'm facing problem at cost loaded
after entering the actual percentges for activities i found the cash flow values for baseline changed and i'm sure that i didn't change the dates for baseline
i appeared the baseline separated and checked the values of cash flow i noted that it became true but after assigning the baseline to my updated schedule the cash flow values are changing
plz if help if you can and tell me what is the reason
thanks
Irfan,
Thanks for commenting. Yes, your suggestion is certainly helpful especially using the "is within range" term.
I aslo wanted to know if it was necessary to aslo incluse a similar "where" clasue for the Finish date and for activities "in progress". I read on another forum that a look ahead schedule should show:
Do others agree with the above? If meeting all three criteria is the correct protocool would the following filter be suitable?
Thanks all,
Regards,
LP6
Hi,
In Primavera P6 ver. 7 have built in filter of Two Week Look Ached Schedule.
If you want to make in manually so here is the procedure of Two Week Look Ahead Sche.
Go to in Filter > Click New > Give a title of your filer > than chek the perameters like this < Where = Start > in within range of > Value = DD > High Value = DD+2W.
Hope this ill help u.
regards