P6 SCHEDULE PROBLEM!!!

Member for

16 years 3 months

You ar enot updating the schedule correctly

If an activity has started check the box nex to started and select the actual start date. If the activity has also finished then also check the box next to finshed and select the actual finish date.

If an activity has started but not yet finished check the box nex to started and select the actual start date and put in the remaing duration.

when you are done with progressing your activities press the F9 button and change the data date to the date that you are recording progress upto.

NOTHING EVER changes until you SCHEDULE the proejct by perfoming the forward and backward pass thats the Tools schedule from the menu or the F9 function button.

You only put in ACTUAL start and end dates you do not put in start and end dates this is the whole point of scheduling the logic and durations determine the start and end dates for activities that ar not started and ro complete.