Microsoft Project Updating - 2 Weeks Only

S
Shane Kelly 👤 Member for 8 years 3 months

Hi All, 

My boss has asked me to provide an update of project porgress for a 2 week timeframe only. This would range from the status date + 2 weeks. When using the 'date range' filter it shows activities that start in this timeframe and finish after it. Is it possible to create a filter to show work complete only in this timeframe. An activity that finishes after this could be 100% complete only within this timeframe but not 100% complete in real terms. Any help or advice would be greatly appreciated? 

Kind Regards

S.K

P
Prial Handig 👤 Member for 15 years

Hi Shane,

One way to do that is to set a baseline of your project and create a filter:

Field Name: "Baseline Finish"

Test: "is less than or equal to"

Value: input the date two weeks ahead from your status date (i.e., if the date today is 2 May '18, then input "16 May '18")

That will show you all the activities that should be completed before and on 16 May '18.

 

Hope this helps.

Regards,

PH

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts