primavera budgeted cost changes

Hi All,

i assigned resources and cost to  my schedule ... but when i enter any actual date in the schedule budgeted total cost gets zero ..

before i didnt come across with this kind of situation.. your help will be appreciated.. 

thanks ina dvance

Z
Zoltan Palffy 👤 Member for 16 years 10 months

1. open the project and select send project and email it to yourself before you do any changes. Its like making a back up if things go haywire.

2. next make sure that the duration type is fixed duration / units per time yours is not add the column for duration type and do a fill down

3. make sure that your activites are task not resource dependent

4. do a global change 

where calcuate costs fron units equal yes

then

calcuate costs from units = no

then select change on the right and then comitt changes

M
müjdat özacar 👤 Member for 17 years

Zoltan,

-my duration type is fixed duration & units.. i follow in that way

-actual units or cost that subtract actual from at completion is checked

-recalculate actual units and cost when duration % complete changes is unchecked because my activity % completion type is physical . i enter actual units or cost manually with real numbers

Z
Zoltan Palffy 👤 Member for 16 years 10 months

make sure that the duration type is set to fixed duration and units/time

also go to PROJECTS and make sure that you project is highlighted and on the calculations tab make sure that under Resource assignments that When updating actual units or cost that subtract actual from at completion is checked and that recalculate actual units and cost when duration % complete changes.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts