Duration % Complete not Rolling Up

E
Emma Lang 👤 Member for 9 years 9 months

Hi Everyone, 

Can anyone suggest a reason why duration % complete isn't rolling up to summary level?

My % complete type is the same for all activities, but I'm unsure what else to check

Thanks

Emma

D
David Kelly 👤 Member for 21 years 7 months

Emma,

Duration % complete does role up.

Activity % complete does not role up, even if all of your % complete types are Duration.

 

 

Z
Zoltan Palffy 👤 Member for 16 years 10 months

The roll up or summarization uses costs to calcuate the % summary complete. You just cant use duration or how many activies are completed its not weighted but if you assign cost then you have a true weigh value and can calculate % complete because you have a basis to do this just having activities by themselves you have no basis to measure against. 

if you are looking at the schedule % complete the Summary % complete when displayed on an organize band, will ALWAYS be calculated as Budget Costs for Work Scheduled X 100 divided by Budget at Completion or (BCWS * 100) / BAC, regardless of what earned value technique is selected for the activity's WBS.

The performance % complete column the Summary % complete when displayed on an organized band will always be calcuated as Budget Costs of Work Performed X 100 or (BCWP • 100) I BAC, regardless of what earned value technique is selected for the activity's WBS.

 

 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts