Hi
Due to policy, our contractor can not create custom calenders. However, due to the nature of the worksite (railway), activities can only occur on certain days.
So my question is. How do you create a programme with correct total float. As using a 7 day calender for an activity that can only occur for example, every 4th weekend give a false float number
They have create a number of milestones for the 'key weekends' SS with the activity. However if you update the programme, you need to then link to the 'next week' should the work not have finished
Hope that makes sense
The incorrect utilization of lags is considered as the principal reason for generated errors when using multi-calendars. It is important to distinguish between two types of lags:
https://mosaicprojects.com.au/PDF/Chronographic_diagramming_method.pdf
Spider Project solves this issue by providing time lag, volume lag and double lags.
excellent idea Paul
I agree with the previouse comments, change the policy. If you are using P6 then allow the contractor to create a Project Calendar. Another option is to create and assign a rresource with a possesion calendar.
Regards
Paul E Harris
I agree with the previouse comments, change the policy. If you are using P6 then allow the contractor to create a Project Calendar. Another option is to create and assign a rresource with a possesion calendar.
Regards
Paul E Harris
You need to talk to whom ever created the policy of not being able to use custom calendars and find out what the reasoning is. This is one of the benefits of using a scheduling program is that you CAN define your working calendars and have multiple calendars. I don't understand why you think that creating a load of milestones can solve your problem the issue is remains the same whether there are milestones or not. You might as well as use a calendar hanging on a wall and put X marks on the day that you can work. If you can not plan your schedule to shows the planned working days your schedule will never be correct. You may as well NOT track the civil work and just add milestones but the problem is that there will be NOTHING driving those milestones. If the civil work is actually on the critical path and you can not accurately reflect that in your plan then it will never show critical.
Hi Mike
Lets assume that chaging policy is not an option, and neither is using some other software
What other ideas are there?
Hi Philip
Any planning software worthy of the name can create such a calendar. (Although P6 may struggle)
The contractor had better change his policy amd his software.
Best regards