Hi,

 

i'm struggling to undertsnad what baseline Acumen Fuse uses when we export from Primavera. I assumed it will be PROJECT BASELINE but even leaving that field set as Current Project it seems to be picking up a date (that isnt the current finish date).

Can someone explain it in laymans terms for me please.

 

A
Andrew Podolny 👤 Member for 21 years 6 months

Use the Assign Baseline command and select the respective file to be assigned as the Baseline:

[[wysiwyg_imageupload:5484:]]

You will see the Symbol B after the Name of your Project in Acumen.

[[wysiwyg_imageupload:5485:]]

Regards,

Andrew

H
h m 👤 Member for 12 years 4 months

Hi

seems P15.2 doesnt export the baseline in the XER file hence a default postion of the Acumen

H
h m 👤 Member for 12 years 4 months

Hi

seems P15.2 doesnt export the baseline in the XER file hence a default postion of the Acumen

Z
Zoltan Palffy 👤 Member for 16 years 10 months

I would assume that you have to tell Acumen what schedule the basline is. Depending on the version of p6 the baseline even though attached DOES NOT come along with p6 export.

My guess is that Acumen wil be using the Late start and late finish dates as baseline dates if a baseline is not provided or identified. 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts