Baseline Schedule Narrative

Dear All,

I need a compreshensive narrative report for the baseline schedule, which inlude detailed understanding for anyone involved in the project.

 

Can anyone please share any sample format/templates for the report.

 

Thanks

Muhammad Zahid

[email protected]

Z
Zoltan Palffy 👤 Member for 16 years 10 months

why not create you own don't ask for others

Baseline CPM Narrative

The  Baseline CPM Network narrative should include the folowing:

 

Ø  Assumptions used in development of the CPM network.

 

Ø  Actions required by others (owner provided permits, owner provided utilities, owner provided access, owner provided equipment, etc..).

 

Ø  The critical and near critical paths.

 

Ø  Description of calendars and how holidays are incorporated.

 

Ø  How the CPM network has accounted for inclement weather.                    

 

Ø  How weather may impact certain activities.

 

Ø  Planned sequencing and phasing.

 

Ø  Anticipated manpower

 

Ø  Over all plan for the project.

 

 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts