Critical Path

I
ind Vid 👤 Member for 10 years 1 month

Hello Experts,

 

What % of total number of activities in a baseline schedule should ideally be lying on the critical path (TF=0), a number from your extensive experience / best practice would suffice.

 

thank you

 

indra

Profile picture for Patrick Weaver
Patrick Weaver 👤 Member for 25 years 4 months

There is no single answer to this - small schedules (low number of activities) will tend to have more activities on the critical path than large schedules, but my heuristic is around 20% is good, below 20% better and knowing the probability of achieving on-time completion is heading 'south' once the percentage gets above 20% (particularly if there are multiple critical paths). 

For more on this see: https://www.mosaicprojects.com.au/WhitePapers/WP1037_Probability.pdf

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts