Hi Seniors,
Mr.Rafel
Mr.zoltan (Sir you have posted a data on this issue in 2014 but I did not get it fully, how)
Mr.Valadmir..................etc
Hope all of you are fine.
I have added a non-labor resource to an activity in my schedule. I want to calculate the cost of units.
- First of all, I want to know what is standard rate & Max unit/time in the resource window (Unit & Price).Its function or how these 2 columns work together in cost loading process.
- how it calculate budgeted cost w.r.t budgeted units in activity window( Resource tab).?
- is our default unit/time & max unit/should be same on any schedule...?
Your earliest response is required
Regards,
Abubakar
there is NO STANDARD rate and MAx units/time you set this based on your resources how they work together is that is you set price per unit to $2/LF and if you have 5 LF of whatever units that will make the costs $2*5=$10
Budgeted costs was already expalined above this will give you your budgeted costs based on the quantity of units.
default units/time & Max units can changed based on the resource being used. Maybe one resource is working 10 hours per day and another is working 8 hours per day.