Problem in material resource budgeted units after importing xer file

Hi Everyone, 

i just imported a xer file, i discovered that durations & budget units of material resources are set to zero, any advice ?

unit price is not zero and calculate cost from units is checked

Best regards,

M
MK TSE 👤 Member for 24 years 3 months

What setting (resource and cost related fields) is selected on Import template?

Z
Zoltan Palffy 👤 Member for 16 years 11 months

also check your duration type make sure it is set to fixed duration & units/time for each activity 

K
Kari Lucas 👤 Member for 15 years 11 months

I'm having the same issue. Version 17.2 is exporting to 15.1. I have 15.2 and when I import the .xer. Some, but not all, of the budgeted units become zero.

C
Casey F 👤 Member for 10 years

I am having the same issue. I loose the budget units when importing, but not consistently.

About a quarter of the resources maintain their budgeted units.

I am running 17.8 exporting as 8.2 per customer requirements.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts