Hi Everyone,
i just imported a xer file, i discovered that durations & budget units of material resources are set to zero, any advice ?
unit price is not zero and calculate cost from units is checked
Best regards,
Hi Everyone,
i just imported a xer file, i discovered that durations & budget units of material resources are set to zero, any advice ?
unit price is not zero and calculate cost from units is checked
Best regards,
What setting (resource and cost related fields) is selected on Import template?
also check your duration type make sure it is set to fixed duration & units/time for each activity
I'm having the same issue. Version 17.2 is exporting to 15.1. I have 15.2 and when I import the .xer. Some, but not all, of the budgeted units become zero.
uncheck calculate costs from units
I am having the same issue. I loose the budget units when importing, but not consistently.
About a quarter of the resources maintain their budgeted units.
I am running 17.8 exporting as 8.2 per customer requirements.