Primavera P6 Schedule Progression and Duration Type

Here's a look at why it is important to set the duration type to fixed duration and units before beginning to progress the schedule in Primavera P6 http://ed.gr/h5p6

Z
Zoltan Palffy 👤 Member for 16 years 10 months

or fixed duration and units/time becasue if you do not and then add resouces then your mahours that you put in for the resource will determine the duration of the activity. 