Hi all, is there a way to add a single predecessor to multiple tasks?
Surely I don't have to go through and add it one by one??!!
Hi all, is there a way to add a single predecessor to multiple tasks?
Surely I don't have to go through and add it one by one??!!
Of course, trusty Excel!
That looks like the route I'll have to take since there are all manner of differing predecessrors on each task. Thanks for your help!
Rob
As I answered a few minutes ago on Stack Exchange:
This won't work if your predecessors already have other successors and your intent is to add a new one. In that case dump the successors column to Excel, manipulate by concatenating strings, then copy/paste back to MSP.