EOTs Concurrency review

E
Ellie R 👤 Member for 10 years 10 months

Have anyone heard anything about concurency review of project finish date?

I know about the concurency review of delays, but I have never heard of project finish date slipage concurency review ! (each of our delay happend in a different period of project and they are not concurent )

Can anyone help here please?

B
Bialla Rafiq 👤 Member for 8 years 7 months

Hi

how we get the concurrent effect while using the time impact analysis ,

We have the updated programmes each month 

suppose Employer delay apear in Jun, 16 - we have the updated programme and we can record the total delays 

We can make the fragnent of delay and can have the impact due to delay of employer , 

But this info give us  the contractor delay before event and employer delay after event 

If we do so for all delays we will get the same delays contractor delays and employers delay- what about concurrency

 

Regards

Bilal

M
Mike Testro 👤 Member for 20 years 5 months

Hi Aqil

You are correct if you are talking about delay effect rather than delay cause.

Best regards

Mike Testro

A
aqil mahmood 👤 Member for 20 years 9 months

Mike

How do u define/see the same time frame in your following  statement

Concurrency is whewhen delay events impact within the same time frame 

as stated by yourself in your previous response as well as supported by SCL  the Concurrent Effect is  where two or more delay events occur in different time zones but each have a delay impact.

from above it is deduced that Employer and Contractor's risk events can occur at any time to produce concurrent effect.

Please clarify.

M
Mike Testro 👤 Member for 20 years 5 months

Hi Aqil

Concurrency is when delay events impact within the same time frame - more or less.

There is no concurrency for a delay at the beginning and another at the end of a project.

Remember concurrency is only an issue if money is involved.

Best regards

Mike Testro

A
aqil mahmood 👤 Member for 20 years 9 months

Mike

If empkoyer risk event (ERE) occuring at early stage for say 100days and contractor risk event (CRE) occuring at a very late stage for say 120 days, and both ERE and CRE are critical delays to completion on parallel critical paths, would they produce a concurrent effect of 100 days? Please clarify

Regards

M
Mike Testro 👤 Member for 20 years 5 months

Hi Ellie

There are two types of concurrency:

1. Concurrent Cause - where two or more delay events occur in the same time zone and each have a delay impact.

2. Concurrent Effect - where two or more delay events occur in different time zones but each have a delay impact.

It seems that your case is Concurrent Effect.

The same rules of allocation of EoT - LAD's & Prologation costs apply in each case.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts