Actual Start Woks before effective date

Dear All Master Primavera<

I am Prastya,  I am is newbie to used primavera P6 in my project and still to learn and explore for this software,

I have problem during making the schedule, because in my project now already start work but the owner not state the effective date yet

Actually at site already work, but I must to insert this actual date to schedule.

 

So How to setting this problem ? (like this picture)

Image removed.

Thanks

 

Regards

 

Prastya

Z
Zoltan Palffy 👤 Member for 16 years 10 months

got to projects directory and change the planned start date of the project