% Complete Column

A
Andy Hudson 👤 Member for 9 years 7 months

Hi,

Please see attached screeenshot (http://ge.tt/7uuG97m2 ). . I previously used it in Asta.

Now I need your help to do so in P6:   

a) How to give Weekly planned % complete column and actual Weekly  % Complete column as I highlighled in rectangle?

b)How to show different weekly progress lines on bar chart at the same time as highlighted in screenshot?

Please advise.

Cheers

Andy

D
David Kelly 👤 Member for 21 years 7 months

Andy,

 

P6 only roles up, indeed only stores % to date for current and baseline schedules. 

A spreadsheet view of quantities forecast per week is simple, but expressing those as percentages is barely possible, making those percentages roll up is impossible.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts