Hi,
Please see attached screeenshot (http://ge.tt/7uuG97m2 ). . I previously used it in Asta.
Now I need your help to do so in P6:
a) How to give Weekly planned % complete column and actual Weekly % Complete column as I highlighled in rectangle?
b)How to show different weekly progress lines on bar chart at the same time as highlighted in screenshot?
Please advise.
Cheers
Andy
Thanks Zoltan and Dave
for planned you have to have a baseline attached
Andy,
P6 only roles up, indeed only stores % to date for current and baseline schedules.
A spreadsheet view of quantities forecast per week is simple, but expressing those as percentages is barely possible, making those percentages roll up is impossible.