I'm newbie in group. I have a problem when update Schedule in Primavera as below. Hope get your clarification, instruction:
* When i update activity in P6 by manual follow these steps:
- Step 1: Create Baseline
- Step 2: Update activity (Depending on report, I updated each activity), i met problem, example with Activity A:
+ In Status Tab (Belong to Activity Detail option): Check started (Actual Started Date = Baseline + 2 days)
--> In right way, Actual Finished Date would be recalculated (Actual Finished Date = Actual Started Date + Duration) before I update Physical % complete and Exp Finish (or Remaining duration). But it did not work, I wondering I forgot or missed some option for this action.
Thanks!
glad I could help
Thanks Zoltan Palffy.
You need to understand scheduling the actual finshed date would never be Actual Finished Date = Actual Started Date + Duration
The Actual Finsh date is a manual unput in the same way that you did when you checked the actual started box and input the actual start date. To get the Actual Finish date you would click the actual finish box and then select the actual finish date.
What I think that you are refering to here is an activity that has an actual start but is not yet completed. In this case you would checked the actual started box and input the actual start date then you would put in the remaining duration regardless of what the physical % compete is.
When you are all done updating you would select tools schedule or press F9 and change the data date to the new date that are recording progress up to.
This wil give you your nre forecasted finish date. If all of the predecessors are completed then the finish date is based off of the Data Date + remaining duration. IT IS NEVER EVER THE ACTUAL FINISH DATE PLUS THE REMAING DURATION.
You need to learn about the forward and backward pass these are how dates are calculated.
Yes, I did.
Dear
Hope u have assigned the Baseline after Step 1