Does the construction materials procurement time get entered into the project plan?

Member for

11 years 4 months

Any one have detailed cinema construction schedule ?

please help the break WBS and activities details

 

Member for

19 years 10 months

Hi Timothy

Yes you should place the procurement duration into your programme.

I use a sub chart with the procurement tasks starting with release of design details followed by:

1. Tender

2. Workshop drawings

3. Approval

4. Manufacture / Procurement

5. Delivery

6. Stock take / storage

These are all linked FS and then linked to the first activity task that needs the materials using an ALAP link.

Then if:

a. The design is late then the progress on site is delayed.

b. If the work is delayed the designer has more time.

Best regards

Mike Testro