Performance % Complete

I received a scedule update using performance % complete in a schedule without resources. Does that make any sense? Isn't performance percent complete related to EVM? How can P6 show PPC when there are no resources in the schedule?

Thank you

Z
Zoltan Palffy 👤 Member for 16 years 10 months

yes the Performance percent complete is used to compute earned value and may be based on the Activity% Complete, on the 0/100 rule, on the 50/50 rule, etc., depending on the technique for computing earned-value percent complete for the activity's WBS. The Performance % Complete specifies what percentage of the activity's planned worth has been earned so far.

since there are no resources Ttis just means that there will not be an earned value calculated. You can still have a performance % complete if you look at the duration % complete or the activity % complete  I bet they are the same numbers as the Performance % complete numbers.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts