I received a scedule update using performance % complete in a schedule without resources. Does that make any sense? Isn't performance percent complete related to EVM? How can P6 show PPC when there are no resources in the schedule?
Thank you
I received a scedule update using performance % complete in a schedule without resources. Does that make any sense? Isn't performance percent complete related to EVM? How can P6 show PPC when there are no resources in the schedule?
Thank you
yes the Performance percent complete is used to compute earned value and may be based on the Activity% Complete, on the 0/100 rule, on the 50/50 rule, etc., depending on the technique for computing earned-value percent complete for the activity's WBS. The Performance % Complete specifies what percentage of the activity's planned worth has been earned so far.