The contract contains multiple unit completion penalty milestones which are waived if the final completion milestone is achieved. The project is in serious delay. The contractor has submitted an EOT claim (TIA and owner delay events only) that is focused on delay to final completion milestone and ignores all the intermediate penalty milestones. In my opinion all penalty milestones should be included in the analysis - any comments please.
Multiple contract milestones
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi Alan
Yes they should.
Instruct your contractor to impact his dely events on the tasks leading to the milestones and refuse to consider anything else until it is done.
Best regards
Mike Testro