Hi,
There are few points which need your help as I am new to P6. Previously used asta powerproject.
a) I made few changes in my schedule but dont want to save these changes. How can I do that in P6?
Previously I used asta which had option save or not saved but in P6 there is no such option to close the project without saving the changes. P6 auto save the changes which is not required.
please suggest.
b)How to move the whole project to a new start date? any tip.
c)How can I hide any single row in P6?
d) How can I do baseline off in my project?
f) How can I do progress off in my whole project?
These all options are easily available in asta powerproject but in p6 facing problem to find the solution of these issues.
Please help
cheers
Andy
glad I could help all you had to do was follow the instructions in my post
Hi Zoltan,
Thanks a lot. Problem solved.
Regards,
Andy yes see your email here
Thanks Zoltan
Tried all but problem not solved to remove data from %Complete Column.
Plesae can I send you my file to see the issue?
Thanks
Thanks Zoltan
Thanks Zoltan
Just last 2 questions. Please reply asap. thank you
a) Regarding ‘How can I do progress off in my whole project?’ means that I assigned the progress to the activities in Performance % complete column. Now I want to remove/clear
What I think you really mean here is how do I destaus my my schedule ?
if you go to time scale and seclect the date interval of Week/day the non working days should be greyed out
This is the forum where all over the world, expert P6 planners reply the complex inquiries but very surprising to see that no one can reply the simple question. Any issue to answer that question or you cant solve this mystry?
See someone reply it or this question remains unswered?
Thanks.
Thanks all for your Help.
Just last 2 questions. Please reply asap. thank you
a) Regarding ‘How can I do progress off in my whole project?’ means that I assigned the progress to the activities in Performance % complete column. Now I want to remove/clear this assigned progress from all activities to make my programme clear. Note : Programme is without labour, materialand cost. see here for progress column with progress input .. http://ge.tt/98nwzal2 ... need to clear that progress in whole column by using global change
The online circulating fixed criteria does not work for my case as shown in snap
When activity Status is not equal to not started
Then;
Actual labour units equal to zero
Actual non labour unit equal to zero
activity status equal to not started.
The above global change is showing that error: Cannot set status to Not Started if activity has actuals.
b)Secondly how to change color of shaded area of Non working days plotted on bar chart? How to do that
Cheers,
Andy
a) I made few changes in my schedule but dont want to save these changes. How can I do that in P6?
many options here
option #1
Undo or delete the project
Option #2
this is a relational database it is constantly saving so you really have no option not to save your work
Option #3
Create a reflection project by going to the Projects directory then highlight the project and right click and select create reflection project. NOW if you are satisfied with the change the reflection project then right click on the project and select merge reflection into source project
b)How to move the whole project to a new start date? any tip.
Go to the Projects directory click on the Dates tab and under PLanned Start change the date there
c)How can I hide any single row in P6?
This is not excel it is a databse no such thing as hiding a row everything in the world revolves and the activity ID so just create a filter
where activity id is not eqaul to (whatever you DO NOT WANT SHOWN)
d) How can I do baseline off in my project?
copy the project then select maintain baseline and then select the project
the select assign baseline
f) How can I do progress off in my whole project?
I do not know what this means
These all options are easily available in P6
a) I made few changes in my schedule but dont want to save these changes. How can I do that in P6? Previously I used asta which had option save or not saved but in P6 there is no such option to close the project without saving the changes. P6 auto save the changes which is not required. please suggest.
b) How to move the whole project to a new start date? any tip.
• Go to the Projects Tab and change the projects planned start.
• Or amend the earliest driving activity possibly via actual or constraint (eg Contract Award)
• Or reschedule to a realistic data date
c) How can I hide any single row in P6?
• Add UDF and fill with text “hide” then create filter to hide those with UDF= “hide”
d) How can I do baseline off in my project?
• Go to Project….. Maintain Baselines
f) How can I do progress off in my whole project?
• Not sure what you mean by this.
If you are going to do work on a P6 schedule and it’s not something you want to keep, create a copy---paste into a sandbox area of the WBS. That way you won’t lose your original. There is no ”save as or “undo” like in Asta
HTH
any expert
Please reply the above.. much appreciate