Hi Planners,
A baseline schedule showing that the start date of the project "milestone task" is not critical "9 days float", some of the succesor tasks has a constraint "start no earlier than". I changed the constraint of those successors to "Must start on" and I got the start date critical. Is there any explanation to this?
Regards,
Moutaz,
Look closely at the early and late dates of your affected tasks.
MSO/MFO constraints in MSP are similar to Mandatory constraints in P6. I avoid them in general. If Total Slack or the "Critical" flag is to be relied on, then you must never assign them to any logically-connected task. I wrote more about this last year: http://wp.me/p6CCB4-7w