Finish date of particular Package got earlier

Hi,

 

Greeting for the day folks,

 

I was updating one of my program and even after increasing data date by 7 days, finish date of particular package got earlier by 27 days, where my project finish date has increased by 7 days as usual. I have ckecked the links , links seems to be good as this program is in use for 5 years and this is the 1st time something like this has happened. 

Please guide me with this.

 

Thanks in advance.

 

Shreeraj

R
Rafael Davila 👤 Member for 22 years 3 months

I also agree with Zoltan.

Make sure there is/was no out-of-sequence progress on any update.  If due to "over-statused"/"out-of-sequence-progress" maybe this can give you a clue.

Out-of-sequence progress is not necessarily a sin, on the contrary it can speed-up a schedule, it can be an improvement on original plan.  I believe out-of-sequence progress shall always be fixed as soon as it happens in order to keep a clear view of schedule logic.

In any case you shall be in control and understand why it happened.

Good Luck.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

it appears that you have over statused your schedule by doing so something else has taken over the critical path

check your progress again and any constraints 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts