P6 DURATION FROM MANHOURS

Z
Zax Cud 👤 Member for 11 years

I developed a schedule from Jobcard, inputted the Resources and Manhours of each activities into the P6 with a daily Work  productive time of 8hrs /day and 7day work week . What am looking for, is there a way the duration will automatically come up based on the information I have provided?

Z
Zoltan Palffy 👤 Member for 16 years 11 months

yes make sure that the duration TYPE is FIXED UNITS/TIME

this way when the budgeted manhours change the durations will change.

P
pankaj mishra 👤 Member for 9 years 5 months

Hey Zax,

 

In case of P6, its not possible , but if you want automatic duration comes then you will try to make a project in Microsoft project and save baseline and update automatically come when you'll putting actual time.

 

 

 

thanks

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts