Each party in the project (buyer or seller) should create a charter from their perspective and pint of views. The business case or why the project has been developed or the objectives etc may be different for each party.
Zoltan, I agree that the charter to be prepared by the upper or higher management, but it needs the approval of the sponsor (if outside entity)
the best way to create a project charter is to have a Partnering meeting with all parties involved in the project and during the partnering meeting create the project charter.
its a "PROJECT CHARTER" not an individaul charter and as Kannan it should be created by the upper management of each party involved in the project.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
I agree with Kannan and Zoltan.
The client can have a project to acquire a service or asset - this project needs defining.
The contractor should have a project to deliver their part of the service or asset - this project needs defining.
The project charter serves to define the project and set authorization limits, see: http://www.mosaicprojects.com.au/WhitePapers/WP1019_Charter.pdf
Kannan
The sponsor should absoulty be involved in creating the charter not and outside participant.
Each party in the project (buyer or seller) should create a charter from their perspective and pint of views. The business case or why the project has been developed or the objectives etc may be different for each party.
Zoltan, I agree that the charter to be prepared by the upper or higher management, but it needs the approval of the sponsor (if outside entity)
Regards
Kannan
the best way to create a project charter is to have a Partnering meeting with all parties involved in the project and during the partnering meeting create the project charter.
its a "PROJECT CHARTER" not an individaul charter and as Kannan it should be created by the upper management of each party involved in the project.
Hi Amro,
Project Charter is required for each party (Client, PMC, Contractor) as each one having different objectives to participate in the same Project.
Project Charter is prepared during the initiation phase by the sponsor and higher management of each party, and its their own document.
Regards
Kannan