Store Period Performance - Calendar Months

I have a new client who have just invested in P6 for the first time (R16.2)

I am in the preocess of setting up to record earned value. Not currently looking to record actuals in P6.

The clients reporting calendar is aligned to calendar months.

Do I have to set up reporting periods aligned to calendar months manually in order to store period performance or is there a quick way to do this?

'Batch Create Financial Periods' doesnt appear to have options for calendar months.

 

Thanks

 

Martin

Z
Zoltan Palffy 👤 Member for 16 years 10 months

set up the financial periods there is a batch create in versin 6.2

then perform a stoer period peformance prior to updating the next period

 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts