I have equipment procurement activities that need to be delivered just in time for each install. I place all the orders on Day 2 of the project. I want to show, for each equipment, a lead time extending upto its install activity (its successor) starting on Day 3 upto Day X where X varies depending on the equipment. I am using P6 R16.2. Using the ALAP constraint is an option, but using it for 15 activities? Any suggestions is most appreciated.
Scheduling Activities Just in Time for Its Successor
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
glad I could help
Thank you, Mr. Palffy, for your reply.
fro equipment delivery using the ALSP is acceptable