Design Deliverable Planning

S
Shaiju Pv 👤 Member for 10 years 6 months

I have project which consists of quite a large  number of drawings.My cliet asked me to incorporate all drawings in the design and deliverables part of the project. Since i have to link all(majority of ) the drawing to construction part and each drawing will go for  two or three revisions from client how do i link to the construction part .

In short :

1. I have drawings, some of them will undergo 2 reviews,some of them will have 3 or more .

2.In this situation how do we link the drawing to the construction

Thanks and regards,

Shijau

 

Z
Zoltan Palffy 👤 Member for 16 years 11 months

design drawings to 30%, then client review 30% drawings then 

design drawings to 60%, then client review 60% drawings then 

design drawings to IFC%, then client review IFC drawings then 

create/submit shop drawings, client review/aprrove shop drawings then

Procurement of whatever material then

install the material

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts