Hi,
Recently I have just amended my resources cost. I want to update my cost baseline by updating the current project by importing previous updated *.xer files. However, when I try to schedule my program it become 0% (except for the 100% activities). Can anyone advise me why does this happen? Or do I have to manually insert in the performance percentage manually one by one to each of the activities. Which by the way consist of more than 500 activities!!!
Thanks in advance guys
glad I could help
Hi Mr Zolfan,
Your method works!! thanks for the reply.
Anderson
Please also Make sure the following:
- No filter has done in the update especially,(in progress activities)
-in update , the option for thechnique computing pecent comletion is custom not 0/100
Good luck
assign the baseline then select update baseline and select costs