Davids solution is an option but there are two other options
option #1
during the importing process select modify then under the Data Type Global change the action to Do Not Import for al of the items listed Resource Codes, Resource Code Values, Roles, Resources and Shift Names.
option #2
go to admin then to Security profiles and then to global profiles and under Privilege UNCHECK the box next to Add Resources.
exit out of P6 get back in and then import the project without this Privilege the rescources CAN NOT be imported.
If you plan on doing this a lot I would suggest that you create another user call it admin1 or something and then make sure that the add resource Privilege box is not checked under this user log in. This way you dont have to keep changing it back and forth.
Member for
16 years 3 monthsthats what I thought no
thats what I thought no senses in have un-necessary resource if you do not need them
Member for
17 years 4 monthsThanks David & Zoltan,My
Thanks David & Zoltan,
My requirement is to avoid the resources while importing. I will try the methods suggested by Zoltan.
Thanks
Kannan
Member for
16 years 3 monthsDavids solution is an option
Davids solution is an option but there are two other options
option #1
during the importing process select modify then under the Data Type Global change the action to Do Not Import for al of the items listed Resource Codes, Resource Code Values, Roles, Resources and Shift Names.
option #2
go to admin then to Security profiles and then to global profiles and under Privilege UNCHECK the box next to Add Resources.
exit out of P6 get back in and then import the project without this Privilege the rescources CAN NOT be imported.
If you plan on doing this a lot I would suggest that you create another user call it admin1 or something and then make sure that the add resource Privilege box is not checked under this user log in. This way you dont have to keep changing it back and forth.
Member for
21 yearsYou should mport the project,
You should mport the project, goto "Enterprise : Resources", filter "Current Project's Resources", select all, delete,