Pls list out the drawbacks of Primavera. ( eg resource assignment can be done automatically depend on the resource availability)
Drawbacks
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
I expected that people will respond to this very interesting question and discuss the way P6 can be improved.
Does weak response mean that everybody is happy with P6 capabilities?
Or it means that most people use P6 for drawing Gantt Charts and do not know about P6 project modeling drawbacks?
My top Four:
It does not have what Spider calls (I think) "Volume" per cent complete
WBS is project specific not Global
Top down planning cannot "nudge" the spending plan
No Cost window (like Resource Assignments but with the expenses)