Forensic Claims Analysis Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Mon, 2017-03-13 12:49 Permalink Hi RonaldThe selected delay Hi Ronald The selected delay analysis method does not depend on the type of construction but on many different factors. The new SCL protocol gives clear guidance on the topic and is essential reading for your thesis. In my opinion selection of the appropriate method(s) for any particular delay analysis is the key skill for an Expert Delay Analyst. Matters to consider include (In no particular Order of Significance): Is it work in progress or completed work. Is it a main contract or sub contract. The contract terms and conditions. Is the programme a contract document or not. Quality of as built records and historic information. Quality of Baseline Programme Use of Software - P6 is rubbish Always avoid a window / time slice method. Best regards Mike Testro Log in or register to post comments
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Mon, 2017-03-13 12:49 Permalink Hi RonaldThe selected delay Hi Ronald The selected delay analysis method does not depend on the type of construction but on many different factors. The new SCL protocol gives clear guidance on the topic and is essential reading for your thesis. In my opinion selection of the appropriate method(s) for any particular delay analysis is the key skill for an Expert Delay Analyst. Matters to consider include (In no particular Order of Significance): Is it work in progress or completed work. Is it a main contract or sub contract. The contract terms and conditions. Is the programme a contract document or not. Quality of as built records and historic information. Quality of Baseline Programme Use of Software - P6 is rubbish Always avoid a window / time slice method. Best regards Mike Testro
Member for
19 years 10 monthsHi RonaldThe selected delay
Hi Ronald
The selected delay analysis method does not depend on the type of construction but on many different factors.
The new SCL protocol gives clear guidance on the topic and is essential reading for your thesis.
In my opinion selection of the appropriate method(s) for any particular delay analysis is the key skill for an Expert Delay Analyst.
Matters to consider include (In no particular Order of Significance):
Is it work in progress or completed work.
Is it a main contract or sub contract.
The contract terms and conditions.
Is the programme a contract document or not.
Quality of as built records and historic information.
Quality of Baseline Programme
Use of Software - P6 is rubbish
Always avoid a window / time slice method.
Best regards
Mike Testro