While updating a schedule, I normally change the actual units manually. This used to work without any hassles until now. At present, I am using a different project as the baseline. When I update the actual units of resources to a new value and press schedule, the actual units go back to the earlier value instead of showing the updated value. Does anyone know why this happens?
Actual Units Update Issue
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
I am using P6.
When I update the progress in my activity and manually insert the actual units, when I schedule the plan, the actuals units overwrite.
Thanks
Friends,
i m also feeling the same problem
Thanks.
what software ?
Hi John,
Have you been able to find the answer to this question. I have the same problem. I have tried to change different settings, but I don't seem to find the correct one.
Thanks