Actual Units Update Issue

While updating a schedule, I normally change the actual units manually. This used to work without any hassles until now. At present, I am using a different project as the baseline. When I update the actual units of resources to a new value and press schedule, the actual units go back to the earlier value instead of showing the updated value. Does anyone know why this happens?

G
Gema Arenas 👤 Member for 9 years 7 months

I am using P6.

When I update the progress in my activity and manually insert the actual units, when I schedule the plan, the actuals units overwrite.

 

Thanks

P
prashant nalawade 👤 Member for 9 years 2 months

Friends,

i m also feeling the same problem 

 

Thanks.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

G
Gema Arenas 👤 Member for 9 years 7 months

Hi John,

 

Have you been able to find the answer to this question. I have the same problem. I have tried to change different settings, but I don't seem to find the correct one.

 

Thanks

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts