Hello,
P6 has a default 8hrs/day (Hours/Time period). If we create a calendar of 10 hrs/day, the duration gets affected because of the default 8hrs/day. What's the best way to fix this.
Regards,
SAN
Hello,
P6 has a default 8hrs/day (Hours/Time period). If we create a calendar of 10 hrs/day, the duration gets affected because of the default 8hrs/day. What's the best way to fix this.
Regards,
SAN
change the calendar that the activity is on
Dear Zoltan,
Thank you for your support. I tried ur lead. But its not working. The dates are the same. i.e., the start date of the successor and the end date of the predecessor are the same for FS relationships like in mentioned in my previous comment.
Regards
Naseeb
Dear Zoltan,
Thank you for your support. I tried ur lead. But its not working. The dates are the same. i.e., the start date of the successor and the end date of the predecessor are the same for FS relationships like in mentioned in my previous comment.
Regards
Naseeb
Dear Zoltan,
Thank you for your support. I tried ur lead. But its not working. The dates are the same. i.e., the start date of the successor and the end date of the predecessor are the same for FS relationships like in mentioned in my previous comment.
Regards
Naseeb
Naseeb
go to tool schedule then options
at the bottom change the calendar for scheduling relationship lag to
Successor activtiy calendar
Hi friends,
I need a help of the similar kind. I have an 8 h/d calender assigned to my project, but with an exception of 6 h/d assigned to one month in between. But for every activities that come along with and after the exception dates are showing problems in their start dates. For eg: for all the FS relations the successors are supposed to start one day after the finish date of the predecessor, but the successor is tarting on the same date the predecesso ends. Also when i give a lag on the activity resource asssignment by say 3 days on the days of exceptions, the start dates shift by 4 or 5 days. I cleared the later problem by giving lags in fractions.
How can i rectify such problems? Will this happen whenever there is an exception to the claender?
PS: I am new in planning. apologies if my question is a blunder
Thanking you in advance
Regards
Naseeb
glad we could help
Thank you.
Regards,
SAN
Assuming you have properly set the Hours per Time Period in your 10-hour calendar ("Time Periods" command), then go to Admin Preferences/Time Periods/Hours per Time Period and check the box for "Use assigned calendar to specify the number of work hours for each time period."
Alternately, you could change the default values in the Admin Preferences.
go to edit users prefrence look under the Time Unist Tab and make sure that they match your calendar