I forgot to write that you shall select colors for each activity type for both finished and future activities. It may be done in the diagram settings window.
For watching movie select to show certain number of day from the project start and uncheck Moment.
thank you for your question and my apology for the delay with the answer. I just returned from the business trip and missed your post.
High rise construction diagram is new and will be improved soon. We did not add its description yet and I will try to describe this functionality in this post.
To get HRCD (High Rise Construction Diagram) create in your construction project new user defined fields with codes store and section. In these fields enter the store where construction activity is performed and in what section. Enter activity types that shall be shown in HRCD.
Look at project Building that is included in the last Spider versions as an example. I suggest to enter actual data in this project to be able to compare current version with the baseline in HRCD.
Now you may open HRCD and push the button Refresh. You will see the settings shown in the next picture. You may select to show project status at certain moment or watch the movie that shows the constructin process at certain period. You may also select if to show both current project and baseline statuses at any moment or only current version. Baseline version may be shown side by side with the current version or overlapping current version in the HRCD. You may also choose what types of work to show in HRCD. For movie select time step (in our case one week was selected).
If you selected to show current moment:
If you watched the movie and stopped it on certain date in the diagram that shows current and baseline schedules side by side:
If you showed current and baseline schedules overlapping:
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
I forgot to write that you shall select colors for each activity type for both finished and future activities. It may be done in the diagram settings window.
For watching movie select to show certain number of day from the project start and uncheck Moment.
Hi Marian,
thank you for your question and my apology for the delay with the answer. I just returned from the business trip and missed your post.
High rise construction diagram is new and will be improved soon. We did not add its description yet and I will try to describe this functionality in this post.
To get HRCD (High Rise Construction Diagram) create in your construction project new user defined fields with codes store and section. In these fields enter the store where construction activity is performed and in what section. Enter activity types that shall be shown in HRCD.
Look at project Building that is included in the last Spider versions as an example. I suggest to enter actual data in this project to be able to compare current version with the baseline in HRCD.
Now you may open HRCD and push the button Refresh. You will see the settings shown in the next picture. You may select to show project status at certain moment or watch the movie that shows the constructin process at certain period. You may also select if to show both current project and baseline statuses at any moment or only current version. Baseline version may be shown side by side with the current version or overlapping current version in the HRCD. You may also choose what types of work to show in HRCD. For movie select time step (in our case one week was selected).
If you selected to show current moment:
If you watched the movie and stopped it on certain date in the diagram that shows current and baseline schedules side by side:
If you showed current and baseline schedules overlapping: