Hi,
I have different projects in Primavera, which make use of the same resources. I want to show the projects in an histogram, with each project a different colour. Does anybody know if this is possible?
In the 'stacked histogram' of resource usage profile, I tried to make use of the filters in the resource usage profile options, but there are no parameters of project, or any other global code. Is it possible to add parameters?
Any other solution within Primavera?
Pierre
it does and I told him to send me his email address and I will send him detailed instruction on how to do this in P6
Rafael that is not P6.
Within large portfolios you might many projects plus different shared pools that migh supply same skill to selected projects:
In such case tabular reports are essential, you need to know from which specific pool and to which specific job the resources are to be moved. When you have many projects running at the same time, each demanding resources from its own set of resourc e pool it is not practical to use histograms.
Pierre
I have detailed instructions on how to create a staked histogram in p6 please send me your email address and I will forward this to you.
Pierre,
As you have already found, the filtering in the stacked histogram is by attributes of the Resource Dictionary only, NOT the resource assignment. That it will only stack "At completion" rather than "Remaining" Units is perhaps an issue you didn't quite get to......
The way that all of my cleints get around this is to use the Report Wizard to build a pivot table directly into Excel, and chart wizard your solution....
[[wysiwyg_imageupload:4623:]]
No doubt knowing the resource allocation per job/project for every resource when your portfolio share resources among different jobs is essential to good resource management. With a report template it is so easy, make use of your software reports if there is no such view available.
look at this blog it shoudl help to do it by resource
https://tensix.com/2017/01/stacked-histograms-in-p6-professional/?platform=hootsuite
Following your suggestion to look for project code parameter but using different software it came out easy if using Tabular Reports and Excel as not all parameters are available for Histogram/Graphical Reports. I suggest you try similar procedure using your software.
Good Luck.
I think you might have to change the role and make the role specific to each project
Yes, but thats per resource, not per project...
In 8.2 you can assign codes to resources and then in the resource useage profle you can grop by that resource code and change the colors per code you can do that with roles also
Hi,
version 8.3.2
Hi,
version 8.3.2
what version are you using ?
Hi,
Thanks for your responds. The roles are the same for most of the resources and projects. Projects do have resources and roles in common, so this is not the solution.
Any other suggestions?
Its hard to believe that Primavera does not have a solution for this. Planning multiple projects, and giving load curves in which projects have an own colour for the load should be pretty normal right?
Pierre
I think that if you assign a different ROLE for each resource for each project that you will able to do this.
the resource can be the same but the role can be different