Level of Effort or WBS Summary

V
Vignesh S 👤 Member for 11 years 1 month

I am in the process of preparing an impacted schedule. For which, I need to break single activity of my baseline schedule into multiple due to constraints experienced during execution.

Foe example. In my baseline shcedule i considered single activity called d-wall works. But, in my impacted schedule I want to split it into 2 like d-wall with utility hindrance and without utility hindrance.

The WBS has further activities like base slab and roof slab construction, so I cannot use WBS summary activity for this. Is it recommended to use Level of Effort activity for this scenario.Also, my requirement is to bring this activity in the critical path. Is it advisable to have LOE activity in Criticla path?

Z
Zoltan Palffy 👤 Member for 16 years 11 months

no nice a loe spans muiliple activities I think you have this backwards you alreayd have a single activity definining it more to describe your delay will only help your case

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts