Hi friends, My MSP Schedule is matched with P6 schedule in terms of duration, Pre & Suc, leads & Lags, resources, calendar. Without leveling the resource, the both MSP and P6 is matched 100%. When enabling the level resource option in Both, P6 dates are not matching with MSP. I need P6 has to match with MSP. Because, MSP is finalized with client. I need to find which option to be enabled in P6 in order to keep the date matched with P6. I am breaking my head for past 2 weeks. Please give me a hint to resolve this. if require, I shall share the files to check the issues. My Mail Id: [email protected]. Regards, Rajkumar
Matching the resource loaded MSP Schedule with Resource loaded P6
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
that would be your best option
Friends,
Thank you so much for you prompt reply.
I understood there is always differences in resource calculations of MSP and P6.
Now i need to proceed with P6 in order to maintaining single control tool of project
Hi,
Thanks a lot for your valuable informations.
I would follow the schedule with resource either with MSP or P6.
Resource leveling using different calculation engines is a sure way to create mismatches, for this reason using different software to manage schedule and to manage risk does not makes much sense.
The differences can be very big.
https://www.stottlerhenke.com/wp-content/uploads/2011/09/2009-10-01_Aur…
By the way if using Spider Project out of the box, without need to look for prioritization rules we get better results than Aurora, P6 and MSP on the eight activities sample schedule, we get the optimal solution.
Tom is correct they will NEVER match 100% get them as close as possible and then adjust accordlingly.
I think there is no solution for your problem.
The available leveling options for MSP and P6 are very different and cannot be perfectly aligned. In addition the leveling rules for MSP are essentially a black box. You may be able to introduce some preferential logic into your P6 schedule to mimic the MSP leveling decisions. Even if you could get perfect alignment between the two tools in a baseline schedule, this alignment would disappear at the first update.
1. Check your durations turn on the decimals they may be different.
2. Check you TIMES go to edit users preference and turn your TIMES on
3. Check you work TIMES in your calendar.
4. Check you Data date TIME.
5. Make sure that you are using a project calendar as opposed to a global calendar and that the calendar matches MSP exactly.