importing resource assignment error

Member for

16 years 4 months

As Nihat Said do not change any order of the columns or format of the columns

you can not ADD a new resource if the resource does not already exist in the database

Member for

23 years 11 months

You might have wrong activity ID or resource IDs specified in the import file.

Also don't change the order of sheets in the XLS file.

Member for

16 years 4 months

make sure that calculate costs from units is set to no. if it is not run a global change and chnage it to no. Also make sure that the resource exists