Importing Xer File

Dear Friends

 

When i import Xer file , the data is imported , how when i schedule it again without making any changes , the dates change

Please advise how can i avoid , as i observe that calender used in import schedule are not in my p6

Need your assistance

 

Best Regards

 

Umer 

Z
Zoltan Palffy 👤 Member for 16 years 11 months

when you import the project during the import process at the update Import Options select modify

in the 3rd section under Data Type: Project where it says calendars change this to Do Not Import and the calendars wil not be imported.

Z
Zoltan Palffy 👤 Member for 16 years 11 months

first guess is that the project is using global calendars vs project calendars. The defaukt calendar that was used and YOUR default calendars are different.

Also your TIMES for your data date may be different

U
Umer Mehmood 👤 Member for 17 years 11 months

Thanks for your comments

 

Please could you elobrate where to select new import confugurration , it would be really helpful

While recheck i found that the previous overirde  function , and my setting were not considering it.

 

thanks

N
Nihat Yildirim 👤 Member for 24 years 6 months

When importing create a new import configuration and in that configuration select insert new for calendars. Make sure that calendars in the XER files are imported.

Also make sure the environment that produced that XER has a similar hours/day setting like yours.  hours/day is typically and by default 8. If you messed with that setting durations would not look right.

 

If you still see the dates are changing then probably the XER is produced before scheduling and dates are not necessarily right just after the import.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts