Query on Task Split (Necking)

Hi guys,

How can I not show a task being splitted when the task is not progressing on schedule in MS project 2016? I used to use Primavera 3.1 and there was an option to remove this "necking". However, I can't seems to find this option in MS project 2016.

Any advice would be appreciated. Thanks in advance!

T
Tom Boyle 👤 Member for 19 years 6 months

Hi Stanley,

I'm editing this to show the best workaround.  Right-click on an empty part of the Gantt Chart graphic and open the Bar Styles list.  Then do the following:

1. Select the bar style to remove the split from (e.g. "Task", "Critical").  Change the "To" column for that style from "Task Finish" to "Early Finish".

2. Select the corresponding split bar style (e.g. "Split", "Critical Split") and either delete it altogether (using the Cut Row button) or Cut/Paste it to a position above the corresponding task bar style on the list.

To avoid corrupting the default views, immediately save as a new view.

[Old, wrong answer. As a workaround, you could try re-formatting the normal and critical split bar styles to the same as the task bar styles - this de-emphasizes the split without completely hiding it.]

In the absence of resource assignments, then you would do well to eliminate the splits altogether.

Good luck, tom 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts