P6 R8.4 Default Project Settings

C
Casey F 👤 Member for 10 years

I am running P6 R 8.4 is there a way to change the settings default when a new project is created?  I am looking to set the default of define critical activites as longest path instead of Total Float less than or equal to.  I work with a variety of skill levels with P6 and it would save a lot of wasted time if I can set the default critical activities to longest path. 

Z
Zoltan Palffy 👤 Member for 16 years 10 months

as a work around is to set everything up in a empty shell project with no activites then just copy it everytime then all your settiings calendar codes ect are there for you. 

C
Casey F 👤 Member for 10 years

Does anyone have an idea on this?  Even if it is to tell me it can't be done?

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts