I am running P6 R 8.4 is there a way to change the settings default when a new project is created? I am looking to set the default of define critical activites as longest path instead of Total Float less than or equal to. I work with a variety of skill levels with P6 and it would save a lot of wasted time if I can set the default critical activities to longest path.
P6 R8.4 Default Project Settings
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
as a work around is to set everything up in a empty shell project with no activites then just copy it everytime then all your settiings calendar codes ect are there for you.
Does anyone have an idea on this? Even if it is to tell me it can't be done?