EOT preparation methodology?

A
ajay k 👤 Member for 9 years 5 months

Dear Experts

Project Scenario - 80% Planned duration surpassed , contractor providing further structural design changes to Sub-contract(**MEP) with existing delay events from contractor i.e ( late civil clearance, civil rework impact and pending approval for delivarables)

Please advise which is the better Delay claim methodology to implement in this type of scenario : As planned + As impacted OR as-built vs as impacted OR Window analysis ( P6 : Approved Baseline or Recovery programme (-) total set of delay events impacting = total duration required to complete overall project)  

**Note : My client is MEP subcontractor

Rgds

Ajay

    

M
Mike Testro 👤 Member for 20 years 5 months

Hi Ajay

How complete are your as built records?

How responsive is the baseline programme?

What are your contract terms?

These are just a few of the things that need to be considered when selecting a dely analysis method.

The one method that works when there is no critical path and only rudimentary as built data is the Projected As Built method.

A demonstration is available for download from my website - www.expertdelayanalysis.com - for £35.00.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts