Hi All
Firstly. I am a lvl 3 planner. And a new one at that. More used to reviewing contractors programmes, than building ones...
So. Question
I am building a programme, where upon only we have a deliverable to be discussed at a weekley meeting
Problem is. We only have two meetings a week. And can only discuss so many deliverables per meeting
If I create a new calender for the meetings, can I create a 'rule' of some king. Ie. If more than 3 deliverables are forecast to the meeting, it will jump to the next one?
Regards
Philip
Thank you. Just need to work out how to do that. I've never used resources in P6
Bit of trial and error :-)
Hi Philip
In most programmes you can put in a resource levelling system on your deliverable resource - allowing only 2 per week.
Best regards
Mike Testro