planning units

dear all,

i created resource excavation budget is 22965 m3 at the beginning of the project & this budget by p6 divided as follows aug. 21872, at Oct. 608 & Nov. 216.

which is not appropriate for the project so i need to adjust it manual per month on P6 as follows:

aug. 10188, at Oct. 7139 & Nov. 5368.

please clarify how can i do it in steps especially the project is active and now i prepared the updated till end of Nov.

regards.

Z
Zoltan Palffy 👤 Member for 16 years 11 months

you have several options

option #1

break the actvity into 3 activites one that occures in Aug one that occurs in Oct and one that occurs in Nov then assign the units to the 3 activiites. What happend to September you totaly skip that month ?

option #2

create a custom curve and then assign that custom curve to that activity. Adjust the percentages in the custom curve to suit your needs. 

Y
yalçın güner 👤 Member for 11 years 1 month

P6 has divided your budgeted units according to its remaining duration. If you want to divide your budget free from duration you have to change your percent complete type I think.

A
abeer mohamed 👤 Member for 9 years 6 months

i need to modify the budget per month manual not the actual or % complete

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts