let me clarify, I have in fact built a commissioning plan (sequneciong by system) on primavera, but i did not get to record progress on commissioning.
so although Ive done the commisioning scheduling work and sat down withthe commissioning team to decide on the wight factors, I never stayed long enough for the commissioning activities to begin.
are you in Oil & Gas in the UAE?
Randa
Hi Randa
Nothing to do with transition planning but I dont understand something. ????
Have you done commisioning or not.
"I’ve never done this before. All my previous experience has been on engineering, procurememnt, construction and commissiong planning."
"Commissioning I believe is done like construction, but you should check on that cause i’m not sure."
PS Transition planning I believe is the same as handing over of a project with other words you first need to do the Procedures Then you need to do the "PIM/PTM" and then you do the Schedule.
Cheers
Cheers