Hi Planners,

Suppose I have 4 days duration activity and the status date is at the end of the second day, the % complete is 75%, this means that only one day remaining which is clear but the bar does not reflect this because the % complete is linked to the actual duration.

How to sort out this and make the actual duration two days and remaining 1 day (in total 3 days)?

Regards,

Muataz

T
Tom Boyle 👤 Member for 19 years 6 months

The link posted by Rafael is an essential resource for anyone moving from OPV to MSP.

The "logic" you expect is based on the existence (and behavior) of the Data Date in OPV, which does not exist in MSP.

As Ron Winter highlights in the document linked by Rafael, the Update Project dialog can be used to impose the consequences of a Data Date on the schedule.  It is, in my view, a necessary (and often tedious) middle step in the update process for an MSP schedule.

As a long-time regular user of both tool sets, I've seen plenty of flaws in both, but I stopped complaining years ago.

M
moutaz aldeib 👤 Member for 22 years 5 months

Unfortunately Tom it is not the same in P6. P6 is more logic in this case once you enter the status data (data date), actual dates and % complete, the remaining duration is calculated automatically.

It is not logic to calculate the remaining duration for each ongoing activity and in the same time the completion date will not move which we will have no indication when the project is expected to be finished.

Regards,

Muataz

T
Tom Boyle 👤 Member for 19 years 6 months

Sorry, MSP does not behave that way, for the reasons I already gave.  By the way, using %complete as an input in the update process should be avoided – it usually leads to partial-day remaining durations that in turn lead to a bunch of unintended consequences.  I thought this is the same issue in both MSP and P6.

M
moutaz aldeib 👤 Member for 22 years 5 months

Thanks Tom, what I am looking for is that the remaining duration is to be calculated by the system once the actual dates, status date and % complete are entered.

Regards,

Muataz

T
Tom Boyle 👤 Member for 19 years 6 months

Moutaz,

You have already answered your own question.

  1. Before updating, insert a colum for "Actual Duration" and a column for "Remaining Duration"
  2. Enter 2 in "Actual Duration"
  3. Enter 1 in "Remaining Duration".  ("Duration" field will reset to 3 days).

Things to remember if you have experience in other tools:

  • MSP has no real Data Date.  Its "Status Date" does not participate directly in any schedule calculations.
  • MSP has no Original Duration.  "Duration" is always the sum of "Actual" and "Remaining" duration.  Changing any one of the three always affects the others.

Good luck. tom

R
Rafael Davila 👤 Member for 22 years 3 months

Maybe as per MSP calculation % Complete is 2 [actual] of 3 [projected total] = 66.67%

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts